Exam 9: Standard Costing: a Functional-Based Control Approach

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Compare and contrast mix and yield variances.

Free
(Essay)
4.8/5
(42)
Correct Answer:
Verified

Substituting direct materials or direct labour produces mix and yield variances.A mix variance is created whenever the actual mix of inputs differs from the standard mix.A yield variance occurs whenever the actual yield or output differs from the standard yield.For direct materials,the sum of the mix and yield variances equals the direct materials usage variance; for direct labour,the sum is the direct labour efficiency variance.The mix variance is the difference in the standard cost of the actual mix of inputs used and the standard cost of the mix of inputs that should have been used.Using a formula,the standard mix quantity can be described as SM = Standard mix proportion * Total actual input quantity.Then,the mix variance will be computed as (AQ - SM) * SP for each component of direct materials.The yield variance is calculated by (standard yield - actual yield) * SP.Standard yield equals the yield ratio multiplied by total actual inputs.The direct labour mix and yield variances are computed in the same manner as the direct materials mix and yield variances.

What will the result be if variable manufacturing overhead is applied based on direct labour hours and there is an unfavourable direct labour efficiency variance?

Free
(Multiple Choice)
4.8/5
(46)
Correct Answer:
Verified

C

Hansenko Company manufactures 100-kilogram bags of fertilizer that have the following unit standard costs for direct materials and direct labour: Direct materials (100@\ 1.00 per kg) \ 100.00 Direct labour (0.5 hours at \ 24 per hour) Total standard direct cost per 100 bag The following activities were recorded for October: - 1,000 bags were manufactured. - 95,000 kg 95,000 \mathrm{~kg} of materials costing $76,000 \$ 76,000 were purchased - 102,500 kg 102,500 \mathrm{~kg} of materials were used. - $12,000 \$ 12,000 was paid for 475 hours of direct labour. There were no beginning or ending work-in-process inventories. a.Compute the direct materials variances. b.Compute the direct labour variances. c.Give possible reasons for the occurrence of each of the preceding variances.

Free
(Essay)
4.9/5
(41)
Correct Answer:
Verified

a.Material price variance:
[$76,000 - (95,000 * $1.00)] = $19,000 F
Material usage variance
[102,500 - 1,000(100)] * $1.00 = $2,500 U
b.Labour rate variance
[$12,000 - (475 hrs.* $24)] = $600
U Labour efficiency variance
[(0.5 * 1,000)- 475 hrs.]$24 = 600 F
c.All of the material price variances could be caused by out-of-date or inappropriate standards.Other potential reasons could be that the firm could be purchasing in larger quantities (larger quantity discounts),the firm could be purchasing lower-grade materials,or the supplier could be forced to offer a lower price due to the economics of the product.
Material usage variance:
Low-quality materials; lower-skilled workers; less-efficient machines; low employee morale.
Labour rate variance:
Higher-skilled workers; longer-tenured workers with higher wages.
Labour efficiency variance:
The firm could be using a more experienced workforce than desired.

Mills Company uses standard costing for direct materials and direct labour.Management would like to use standard costing for variable and fixed overhead. The following monthly cost functions were developed for manufacturing overhead items: Indirect materials \ 1.00 per DLH Indirect labour \ 1.25 per DLH Utilities \ 0.50 per DLH Insurance \ 10,000 Depreciation \ 40,00 The cost functions are considered reliable within a relevant range of 20,000 to 40,000 direct labour hours.The company expects to operate at 25,000 direct labour hours per month. Information for the month of June is as follows: Actual overhead costs incurred: Indirect materials \ 20,000 Indirect labour 30,000 Utilities 12,000 Insurance 11,000 Depreciation 40,000 Total \ 113,000 Actual direct labour hours worked: 24,000 Standard direct labour hours allowed for production achieved: 27,000 a.Calculate the following standard manufacturing overhead rates based upon expected capacity: i.Variable manufacturing overhead ii.Fixed manufacturing overhead rate iii.Total manufacturing overhead rate b.Calculate the following variances: i.Variable overhead spending variance ii.Variable overhead efficiency variance iii.Fixed overhead spending variance iv.Fixed overhead volume variance c.Prepare the journal entries to record and apply overhead costs.Solution includes the record of overhead costs as well as the entries necessary to close variance accounts.

(Essay)
4.9/5
(43)

Which of the following factors would cause a labour quantity variance?

(Multiple Choice)
4.9/5
(36)

How are standards developed? What is the difference between ideal and currently attainable standards?

(Essay)
4.7/5
(29)

Bender Corporation produced 100 units of Product AA. The total standard and actual costs for materials and direct labour for the 100 units of Product AA are as follows: Materials: Standard Actual Standard: 200 kilograms at \ 3.00 per kilogram \ 600 Actual: 220 kilograms at \ 2.85 per kilogram \6 27 Direct labour: Standard: 400 hours at \ 15.00 per hour 6,000 Actual: 368 hours at \ 16.50 per hour 6,072 -Refer to the figure.What is the material usage variance for Bender Corporation?

(Multiple Choice)
4.9/5
(40)

Regis Corporation uses two materials in the production of its product. The materials, X \mathrm{X} and Y \mathrm{Y} , have the following standards: Material Standard Mix Standard Unit Price Standard Cost 3,500 units \ 1.00 per unit \ 3,500 1.500 units 3.00 per unit \ 4.500 Yield 4,000 units  During April, the following actual production information was provided: \text { During April, the following actual production information was provided: } Material Actual Mix 30,000 units 20,000 units Yield 36,000 units -Refer to the figure.What is the labour mix variance?

(Multiple Choice)
4.9/5
(26)

Which of the following factors would cause an unfavourable material quantity variance?

(Multiple Choice)
4.8/5
(41)

What is the unit standard cost?

(Multiple Choice)
4.8/5
(35)

Frekko Company collected the following information: Standard costs per unit: Variable overhead 4 machine hours @ \6 per machine hour Fixed overhead 4 machine hours @\ 10 per machine hour Actual output 20,000 units Denominator (normal capacity) output 21,000 units Actual machine hours 79,000 machine hours Actual variable overhead cost \ 540,000 Actual fixed overhead cost \ 810,000 -Refer to the figure.Using the two variance method,what is the budget variance?

(Multiple Choice)
4.9/5
(36)

The following standard costs were developed for one of the John Miller Company's products: STANDARD COST CARD PER UNIT Materials: 10 kilograms \times\ 8 per kilogram \ 80.00 Direct labour: 3 hours \times\ 32 per hour 96.00 Variable manufacturing overhead: \ 20 per hour ? Fixed manufacturing overhead ? Total standard cost per unit ? The following information is available regarding the company's operations for the period: Units produced: 15,000 Materials purchased: 180,000 kilograms @\ 7.20 per kilogram Materials used: 160,000 kilograms Direct labour: 18,000 hours @,\ 37.00 per hour Manufacturing overhead incurred: Variable \ 880,000 Fixed \ 2.560.000 Budgeted fixed manufacturing overhead for the period is $2,400,000,and expected capacity for the period is 40,000 direct labour hours. a.Calculate the standard fixed manufacturing overhead rate. b.Complete the standard cost card for the product.

(Essay)
5.0/5
(39)

Reynolds Manufacturing Company has the following information pertaining to a normal monthly 10,000 units. Standard factory overhead rates are based on a normal monthly volume of one standard direct hour per unit. Standard factory overhead rates per direct labour hour are: Fixed \ 6.00 Variable 10.00 \1 6.00 Units actually produced in current month 9,000 units Actual factory overhead costs incurred (includes \ 70,000 fixed) \ 156,000 Actual direct labour hours 9000 hours -Refer to the figure.What is the variable overhead spending variance for Reynolds?

(Multiple Choice)
4.9/5
(32)

Frekko Company collected the following information: Standard costs per unit: Variable overhead 4 machine hours @ \6 per machine hour Fixed overhead 4 machine hours @\ 10 per machine hour Actual output 20,000 units Denominator (normal capacity) output 21,000 units Actual machine hours 79,000 machine hours Actual variable overhead cost \ 540,000 Actual fixed overhead cost \ 810,000 -Refer to the figure.Using the two variance method,what is the total variance?

(Multiple Choice)
4.8/5
(30)

What do variances indicate?

(Multiple Choice)
4.9/5
(39)

Gina Production Company uses a standard costing system.The following information pertains to the current year. Actual factory overhead costs (\ 16,500 is fixed) \1 0,125 Actual direct labour costs (11,250 hours) \1 31,625 Standard direct labour for 5,500 units: Standard hours allowed 11,000 hours Labour rate \1 2.00 The factory overhead rate is based on an activity level of 10,000 units.Standard cost data for 5,000 units is as follows: Variable factory overhead \ 22,500 Fixed factory overhead Total factory overhead What is the variable overhead efficiency variance for Gina Production Company?

(Multiple Choice)
4.7/5
(40)

Harry Company's standard variable overhead rate is $6 per direct labour hour,and each unit requires 2 standard direct labour hours.During March,Harry recorded 6,000 actual direct labour hours,$37,000 actual variable overhead costs,and 2,900 units of product manufactured. What is the total variable overhead variance for March for Harry?

(Multiple Choice)
4.9/5
(34)

Which of the following people is most likely responsible for an unfavourable variable overhead efficiency variance?

(Multiple Choice)
4.8/5
(27)

Max Company has developed the following standards for one of its products. Direct materials: 15 kilograms \times\ 16 per kilogram Direct labour: 4 hours \times\ 24 per hour Variable manufacturing overhead: 4 hours \times\ 14 per hour The following activity occurred during the month of October: Materials purchased: 10,000 kilograms costing \ 170,000 Materials used: 7,200 kilograms Units produced: 500 units Direct labour: 2,300 hours at \ 23.60/ hour Actual variable manufacturing overhead: \ 30,000 The company records materials price variances at the time of purchase. What is the direct materials price variance?

(Multiple Choice)
4.8/5
(38)

What is total fixed overhead budget variance always equal to?

(Multiple Choice)
4.8/5
(47)
Showing 1 - 20 of 86
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)