Exam 11: Standard Costs and Variance Analysis
Exam 1: The Role of Ethical Accounting Information in Management Decision Making116 Questions
Exam 2: Cost Concepts, Behaviour, and Estimation171 Questions
Exam 3: Cost-Volume-Profit Analysis185 Questions
Exam 4: Relevant Information for Decision Making165 Questions
Exam 5: Job Costing168 Questions
Exam 6: Process Costing143 Questions
Exam 7: Activity-Based Costing and Management183 Questions
Exam 8: Measuring and Assigning Support Department Costs139 Questions
Exam 9: Joint Product and By-Product Costing142 Questions
Exam 10: Static and Flexible Budgets164 Questions
Exam 11: Standard Costs and Variance Analysis166 Questions
Exam 12: Strategic Investment Decisions136 Questions
Exam 13: Pricing Decisions127 Questions
Exam 14: Strategic Management of Costs101 Questions
Exam 15: Measuring and Assigning Costs for Income Statements158 Questions
Exam 16: Performance Evaluation and Compensation77 Questions
Exam 17: Strategic Performance Measurement138 Questions
Exam 18: Sustainability Management74 Questions
Select questions type
Pardee, Inc. completed operations for the week and the accountant was preparing to make journal entries necessary to prepare a set of interim financial statements. Unfortunately, he discovered some of the data concerning direct materials had been lost. He was able to find the following: Efficiency variance $4,500 Unfavourable
Standard price $10 per unit
Actual units purchased 9,000
Inventory decrease 1,000 units
Budget variance $900 Favourable
The standard quantity of direct materials allowed for the month was:
(Multiple Choice)
4.8/5
(26)
Boulder Corporation uses a standard costing system. The following factory overhead and production data were reported in September: Standard fixed overhead allocation rate per direct labour hour $2
Estimated monthly direct labour hours 40,000
Standard direct labour hours for actual output in September 42,000
The fixed overhead production volume variance is:
(Multiple Choice)
4.8/5
(36)
Hogle Mfg. Co. uses a standard costing system. The standard time to produce one unit is 4 hours, and normal production is 3,000 units monthly. Overhead costs were estimated to be $135,000. The standard variable overhead rate is $5 per machine hour. During April the following results were recorded: Units produced 3,100
Units sold 2,800
Machine hours required 12,800
Actual overhead costs $136,000
The fixed overhead production volume variance was:
(Multiple Choice)
4.8/5
(40)
The fixed overhead budget variance can be broken down into two parts: the spending variance and the production volume variance.
(True/False)
4.8/5
(39)
Hogle Mfg. Co. uses a standard costing system. The standard time to produce one unit is 4 hours, and normal production is 3,000 units monthly. Overhead costs were estimated to be $135,000. The standard variable overhead rate is $5 per machine hour. During April the following results were recorded: Units produced 3,100
Units sold 2,800
Machine hours required 12,800
Actual overhead costs $136,000
The total overhead allocated was:
(Multiple Choice)
4.8/5
(29)
Unreasonable standards may be the cause of direct materials variances, but not of direct labour variances.
(True/False)
4.9/5
(32)
A standard cost variance is a difference between a standard cost and an actual cost.
(True/False)
4.9/5
(37)
Vashon Corporation had the following activity during a recent period: Standard quantity of direct materials 9,000 kilograms
Actual quantity of direct materials purchased and used 8,800 kilograms
Efficiency variance $2,400 favourable
Total direct materials budget variance $200 favourable
The standard price per kilogram was:
(Multiple Choice)
4.8/5
(34)
Hyteck, Inc. is a capital intensive firm. Indirect costs make up nearly 70% of the product costs. The company has no direct material costs because customers provide the direct materials used for each job. To plan and control such costs, the firm employs flexible budgets and standard costs. Overhead rates, based on direct labour hours, are derived from the master budget. Master Actual
Budget Results
Units produced 2,000 1,820
Direct labour hours 10,000 9,200
Fixed overhead $100,000 $98,000
Variable overhead $160,000 $150,000
Direct labour $100,000 $90,000
The variable overhead spending variance was:
(Multiple Choice)
4.9/5
(33)
Everett, Inc. budgeted $1,488,000 for total overhead. The standard variable overhead rate was $2 per direct labour hour, or $6 per unit, based on an anticipated activity level of 600,000 direct labour hours. During the year 220,000 units were produced. Fixed overhead costs incurred were $300,000. The variable overhead budget variance was $19,800 unfavourable, and the actual variable overhead rate was $2.10 per direct labour hour. The fixed overhead budget variance was:
(Multiple Choice)
4.9/5
(43)
If a variance analysis shows that operations are better than expected, managers should:
(Multiple Choice)
5.0/5
(41)
During the period Richeleau produced 1,000 units of product. The flexible budget for standard costs is: Direct materials $43,000
Direct labour 67,000
Variable overhead 30,000
Fixed overhead 25,000
Variances for the period are:
Direct materials price $ 400 U
Direct materials efficiency 500 F
Direct labour price 600 F
Direct labour efficiency 200 U
Variable overhead spending 300 F
Variable overhead efficiency 100 F
Fixed overhead spending 500 F
Fixed overhead production volume 1,000 U
The direct materials inventory increased during the period by 1,000 (at standard cost). What was the actual cost of direct materials purchased during the period?
(Multiple Choice)
4.9/5
(34)
Henton, Inc. budgeted $270,000 for overhead. Based on a normal activity level of 6,000 units and a standard of 3 machine hours per unit, the standard fixed overhead allocation rate is $12 per machine hour. During the current period, 6,200 units were produced and 5,600 units were sold. Actual machine hours were 18,000, and actual overhead was $272,000.
a)Calculate the combined variable and fixed overhead spending variance.
b)Calculate the variable overhead efficiency variance.
c)Calculate the fixed overhead production volume variance.
d)By how much was total overhead overapplied or underapplied?
e)Explain why actual overhead costs are usually different than budgeted overhead costs.
f)Explain why managers do not need to investigate a variable overhead efficiency variance, regardless of its materiality.
(Essay)
4.9/5
(42)
If a variance is investigated and determined to be random, managers should:
(Multiple Choice)
4.8/5
(39)
Fixed overhead costs are not expected to vary with production volumes. Therefore, production volume variances:
(Multiple Choice)
4.9/5
(40)
If a variance is considered material, it should be allocated to work in process inventory, finished goods inventory, and cost of goods sold.
(True/False)
4.9/5
(44)
Showing 141 - 160 of 166
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)