Exam 12: Building Information Systems and Managing Projects
Exam 1: Business Information Systems in Your Career100 Questions
Exam 2: Global E-Business and Collaboration100 Questions
Exam 3: Achieving Competitive Advantage With Information Systems100 Questions
Exam 4: Ethical and Social Issues in Information Systems100 Questions
Exam 5: It Infrastructure: Hardware and Software100 Questions
Exam 6: Foundations of Business Intelligence: Databases and Information Management100 Questions
Exam 7: Telecommunications, the Internet, and Wireless Technology100 Questions
Exam 8: Securing Information Systems100 Questions
Exam 9: Achieving Operational Excellence and Customer Intimacy: Enterprise Applications100 Questions
Exam 10: E-Commerce: Digital Markets, Digital Goods100 Questions
Exam 11: Improving Decision Making and Managing Knowledge100 Questions
Exam 12: Building Information Systems and Managing Projects100 Questions
Select questions type
________ provides a model for an information system solution and consists of all the specifications that will deliver the functions identified during systems analysis.
(Multiple Choice)
4.8/5
(37)
A test plan begins by testing how well the entire system works and identifying where it fails.
(True/False)
4.7/5
(37)
Systems analysts typically gather facts about existing systems by interacting with end users.
(True/False)
4.7/5
(39)
Domestic outsourcing is driven primarily by the fact that outsourcing firms possess skills, resources, and assets that their clients do not have.
(True/False)
4.8/5
(39)
What qualities of object-oriented development make this method especially suitable for Internet applications?
(Essay)
4.9/5
(36)
Object-oriented development could potentially reduce the time and cost of writing software because:
(Multiple Choice)
4.8/5
(34)
Which is the last step in developing a new information system?
(Multiple Choice)
4.8/5
(42)
You are an IT project manager for an advertising firm. The firm wishes to create an online survey tool that will be used to survey focus group reactions to products in development. The most important consideration for the firm is being able to offer the tool as soon as possible as a new corporate service. However, you know that many of the senior managers that are business owners of this project have difficulty in understanding technical or software development issues, and are likely to change their requirements during the course of development. What development method would be most successful for this project?
(Multiple Choice)
4.8/5
(39)
If an organization's requirements conflict with the software package chosen, and the package cannot be customized, the organization should:
(Multiple Choice)
4.8/5
(40)
In an object-oriented development framework for a university, how would the classes Degree, Mathematics, and Physics be related?
(Multiple Choice)
4.8/5
(34)
The entire system-building effort begins with and is driven by:
(Multiple Choice)
4.8/5
(28)
One problem with prototyping is that the systems constructed may not be able to handle large quantities of data in a production environment.
(True/False)
4.8/5
(34)
Gantt and PERT charts are two common formal planning tools for project management.
(True/False)
4.8/5
(36)