    The Sum of Activity Durations of the Longest Path in a Network
Solved

The Sum of Activity Durations of the Longest Path in a Network

Question 29

Question 29

True/False

The sum of activity durations of the longest path in a network indicates expected project completion time,and the activities on it are called the critical activities.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q19: Only activities on the critical path are

Q24: The Project Manager is about to begin

Q25: The manager of a National Forest is

Q26: Activities not on the critical path have

Q26: Project managers bear the ultimate responsibility for

Q27: Risk assessment is part of the project

Q30: The standard deviation of the duration of

Q31: The project management technique that is repeated

Q33: The owner of Ace Building Co.is about

Q34: Activity 4 in a network diagram has

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines