Multiple Choice
The owner of Ace Building Co.is about to begin work on a project comprised of the following four activities: What is the estimated expected (mean) duration for activity D?
A) 32 days
B) 41 days
C) 44 days
D) 42 days
E) 40 days
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q19: Only activities on the critical path are
Q26: Activities not on the critical path have
Q29: The sum of activity durations of the
Q30: The standard deviation of the duration of
Q31: The project management technique that is repeated
Q34: Activity 4 in a network diagram has
Q35: At which point does crashing of a
Q36: Consecutive activities on the same path have
Q37: The manager of a National Forest is
Q38: The owner of Ace Building Co.is about