The project management technique that is repeated until activities are decomposed into work packages that can be performed by a designated worker,team or subcontract is called:
A) work breakdown structure (WBS) .
B) program evaluation and review technique (PERT) .
C) planning matrix.
D) crashing.
E) project scheduling