Which of the Following Is the Last Step in Project

Question 131

Multiple Choice

Which of the following is the last step in project portfolio selection?


A) Collect project data
B) Assess resources
C) Prioritize projects within categories
D) Provide reasons for selection or non-selection of each project
E) Project closeout