Multiple Choice
Which of the following is not a part of project scheduling?
A) Identify resource requirements for activities
B) Estimate the duration of activities
C) Identify activities in the work breakdown structure
D) Identify sequential dependencies among activities
E) Risk management planning
Correct Answer:

Verified
Correct Answer:
Verified