A Project Superintendent Is About to Begin Work on a Freeway

Question 55

Multiple Choice

A project superintendent is about to begin work on a freeway resurfacing project,which is comprised of the following five activities: A project superintendent is about to begin work on a freeway resurfacing project,which is comprised of the following five activities:   What is the probability that the critical path for this project will be completed within 52 weeks? A) 0.1554 B) 0.3108 C) 0.3466 D) 0.6554 E) 0.8277 What is the probability that the critical path for this project will be completed within 52 weeks?


A) 0.1554
B) 0.3108
C) 0.3466
D) 0.6554
E) 0.8277