Multiple Choice
A project superintendent is about to begin work on a freeway resurfacing project,which is comprised of the following five activities: What is the probability that the critical path for this project will be completed within 52 weeks?
A) 0.1554
B) 0.3108
C) 0.3466
D) 0.6554
E) 0.8277
Correct Answer:

Verified
Correct Answer:
Verified
Q50: What are the estimated expected (mean)durations (in
Q51: Given this information about activity B: ES
Q52: A project manager for Durable Construction Co.is
Q53: A project superintendent is about to begin
Q56: What is the estimated standard deviation (in
Q57: A PERT/CPM activity has an optimistic duration
Q58: The standard deviation of a project duration
Q59: Which of the following is not a
Q60: What are the estimated standard deviations (in
Q88: Activity C has an early start time