Multiple Choice
Besides project activities,the primary information that all Gantt charts illustrate is:
A) project budget and when activities occur.
B) cost of activities and delays in the schedule.
C) planned duration of activities and when they occur in the schedule.
D) project budget and staffing levels.
E) critical path and project budget.
Correct Answer: