A project superintendent is about to begin work on a freeway resurfacing project,which is comprised of the following five activities: What is the estimated expected (mean) duration for project completion?
A) 35 weeks
B) 39 weeks
C) 50 weeks
D) 104 weeks
E) 105 weeks