A project superintendent is about to begin work on a freeway resurfacing project,which is comprised of the following five activities: What is the estimated expected (mean) duration for Activity E?
A) 31 weeks
B) 38 weeks
C) 39 weeks
D) 40 weeks
E) 43 weeks