Multiple Choice
The Project Manager is about to begin a project comprised of the following six activities: What is the estimated standard deviation of the duration for activity E?
A) 2 days
B) 3 days
C) 4 days
D) 16 days
E) 24 days
Correct Answer:

Verified
Correct Answer:
Verified