Solved

The Project Manager Is About to Begin a Project Comprised

Question 44

Multiple Choice

The Project Manager is about to begin a project comprised of the following six activities: The Project Manager is about to begin a project comprised of the following six activities:   What is the estimated standard deviation of the duration for activity E? A) 2 days B) 3 days C) 4 days D) 16 days E) 24 days What is the estimated standard deviation of the duration for activity E?


A) 2 days
B) 3 days
C) 4 days
D) 16 days
E) 24 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions