Multiple Choice
The Project Manager is about to begin a project comprised of the following six activities: What is the estimated slack time for the path A-D-F?
A) 0 days
B) 20 days
C) 40 days
D) 60 days
E) 100 days
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q37: The manager of a National Forest is
Q38: The owner of Ace Building Co.is about
Q39: Which of the following is not involved
Q40: Activity 7 is directly preceded by two
Q41: Which of the following would probably not
Q43: In a precedence network the critical path
Q44: The Project Manager is about to begin
Q45: A beta distribution can be used to
Q47: A relatively simple tool for planning and
Q71: The earliest finish time for an activity