Question 42

Multiple Choice

The Project Manager is about to begin a project comprised of the following six activities: The Project Manager is about to begin a project comprised of the following six activities:   What is the estimated slack time for the path A-D-F? A) 0 days B) 20 days C) 40 days D) 60 days E) 100 days What is the estimated slack time for the path A-D-F?


A) 0 days
B) 20 days
C) 40 days
D) 60 days
E) 100 days