Multiple Choice
A relatively simple tool for planning and scheduling simple projects is the:
A) an activity-on-arrows network.
B) an activity-on-nodes network.
C) a Gantt chart.
D) critical path method.
E) program evaluation and review technique.
Correct Answer:

Verified
Correct Answer:
Verified