Multiple Choice
A project superintendent is about to begin work on a freeway resurfacing project,which is comprised of the following five activities: What is the estimated slack time for Activity E?
A) 0 weeks
B) 3 weeks
C) 9 weeks
D) 11 weeks
E) 12 weeks
Correct Answer:

Verified
Correct Answer:
Verified