Multiple Choice
A project manager for Durable Construction Co.is about to build a house involving the following six activities: What is the probability that the critical path for this project will be completed within 210 days?
A) 0.5000
B) 0.8413
C) 0.9544
D) 0.9772
E) 0.9987
Correct Answer:

Verified
Correct Answer:
Verified
Q47: A relatively simple tool for planning and
Q48: In crashing this project to 18 weeks,which
Q49: Once a project is underway,project managers are
Q50: What are the estimated expected (mean)durations (in
Q51: Given this information about activity B: ES
Q53: A project superintendent is about to begin
Q55: A project superintendent is about to begin
Q56: What is the estimated standard deviation (in
Q57: A PERT/CPM activity has an optimistic duration
Q88: Activity C has an early start time