Solved

A Project Manager for Durable Construction Co

Question 52

Multiple Choice

A project manager for Durable Construction Co.is about to build a house involving the following six activities: A project manager for Durable Construction Co.is about to build a house involving the following six activities:   What is the probability that the critical path for this project will be completed within 210 days? A) 0.5000 B) 0.8413 C) 0.9544 D) 0.9772 E) 0.9987 What is the probability that the critical path for this project will be completed within 210 days?


A) 0.5000
B) 0.8413
C) 0.9544
D) 0.9772
E) 0.9987