Multiple Choice
In the drum-buffer-rope conceptualization used in the theory of constraints,the "buffer" refers to:
A) inventory just before the bottleneck.
B) the bottleneck of the process.
C) total capacity of the process.
D) first stage in the process.
E) the master schedule.
Correct Answer:

Verified
Correct Answer:
Verified