Multiple Choice
Which of the following is not a measure for judging the effectiveness of a schedule sequence?
A) Average work-in-process
B) Total processing time
C) Job flow time
D) Job lateness
E) average hours or days late
Correct Answer:

Verified
Correct Answer:
Verified