Multiple Choice
The owner/operator of the local franchise of Handyman,Inc.,has four jobs to do today,shown in the order they were received: If he uses the earliest due date first (EDD) priority rule to schedule these jobs,what will be the average job lateness?
A) 0 hours
B) 1.5 hours
C) 1.75 hours
D) 2 hours
E) 2.25 hours