Multiple Choice
A primary reason why staff scheduling in services can be more challenging than it is for manufacturing is:
A) services have less processing variability.
B) services cannot be inventoried.
C) people generally are willing to wait longer for manufactured products.
D) customers will not wait for services.
E) all services use appointments that have to match customers' schedules.
Correct Answer:

Verified
Correct Answer:
Verified