Multiple Choice
Which of the following is not a method to reduce scheduling difficulty?
A) Set realistic due dates
B) Adapt the schedule to changing customer requirements
C) Focus in bottleneck operations
D) Use scheduling software
E) Use shop floor control
Correct Answer:

Verified
Correct Answer:
Verified