Multiple Choice
The operations manager of a body and paint shop has five cars to schedule for repair.He would like to minimize the make-span to complete all work on these cars.Each car requires body work prior to painting.The estimates of the times required to do the work at each of the two stations are as follows: Using Johnson's rule what is the optimum sequence (first car to last) ?
A) A; B; C; D; E
B) E; D; C; B; A
C) E; B; D; C; A
D) E; D; B; C; A
E) E; B; D; A; C
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Which of the following is not a
Q2: First come,first served (FCFS)is an example of
Q3: Given the following data for jobs awaiting
Q5: The Theory of Constraints focuses on _.<br>A)work-in-process
Q6: A primary reason why staff scheduling in
Q7: The following questions refer to the table
Q8: The following questions refer to the table
Q9: A schedule/control Gantt chart depicts jobs or
Q10: In the production planning hierarchy,scheduling is the
Q11: Given the following information concerning jobs awaiting