A firm operates a flow shop building kitchen cabinetry for recreational vehicles. The major activities of this process are listed below.
a. Draw the appropriate network for this project.
b. What would the cycle time be if the goal is to produce 20 units per month (the plant operates
160 hours per month)?
c. What is the theoretical minimum number of workstations needed?
d. Balance with the most following tasks heuristic. What tasks are assigned to which stations?
e. What is the efficiency of the line obtained in part d?
Correct Answer:

Verified
(b) The cycle time is 160/20=8 hours; ...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q39: The main issue in designing process layouts
Q41: Takt time is<br>A) the total work time
Q57: Hemo-tech, Inc., a biomedical technology and research
Q63: An assembly line is assigned as follows.
Q65: There are three work centers (A, B,
Q126: Which of the following is <b>true </b>regarding
Q126: A(n) _ is a special product-oriented arrangement
Q131: The most common tactic followed in process-layout
Q210: What design guidelines help retail layouts to
Q289: The most common tactic to arrange departments