Essay
Hemo-tech, Inc., a biomedical technology and research laboratory, produces a standard blood filtering device on an assembly line basis. Six basic tasks are performed along an assembly line. The time to perform each task and the tasks that must immediately precede each task are in the table below. Twenty pumps per 450-minute day must be produced by the assembly line.
a. Draw the network diagram of the precedence relationships.
b. Identify the absolute minimum and maximum cycle times.
c. How many workstations are required to meet the schedule?
d. What is the cycle time required to meet demand?
e. Balance this line using most following tasks heuristic.
f. What is the efficiency of the line obtained in part e?
g. Can the efficiency of this solution be improved? Explain.
Correct Answer:

Verified
(a) The appropriate diagram appears belo...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q3: Utilization of the total "cube" is the
Q39: The main issue in designing process layouts
Q41: Takt time is<br>A) the total work time
Q58: Category management is the use of computer
Q61: A firm operates a flow shop building
Q63: An assembly line is assigned as follows.
Q87: Which of the statements below best describes
Q123: What is cross-docking?<br> Why is it appropriate
Q126: Which of the following is <b>true </b>regarding
Q210: What design guidelines help retail layouts to