Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below.
a. What is the crash cost per unit time for each of the three activities?
b. Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost?
c. Which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost?
Correct Answer:

Verified
(a) crash cost X = $1,000 per ...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q12: Gantt charts give a timeline for each
Q14: Every network has at least one critical
Q31: A simple CPM network has three activities,A,B,and
Q35: Which of the following statements regarding critical
Q74: The Beta distribution is used in project
Q75: Analysis of a PERT problem shows the
Q80: An activity on a PERT network has
Q91: An activity on a PERT network has
Q92: Identify the responsibilities of project managers.
Q115: Which of the following statements regarding time-cost