Multiple Choice
The critical path for the network activities shown below is ________ with duration ________.
A) A-B-D;10
B) A-B-E;11
C) C-E;12
D) A-D-E;13
E) A-B-C-D-E;22
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q13: If an activity whose normal duration is
Q29: PERT calculations typically include the duration variance
Q32: An activity on a PERT network has
Q35: What is the basic difference between PERT
Q47: Two critical path activities are candidates for
Q48: Two critical path activities are candidates for
Q79: Describe the differences between a Gantt chart
Q88: If an activity whose normal duration is
Q103: Activity R on a CPM network has
Q119: The critical path can be determined by