Multiple Choice
Table 11-8
A mad scientist has identified the ten steps required to create a race of atomic supermen to complete his plans for world conquest.The estimated time in weeks and cost in US dollars appear in the table along with the shortest possible duration for each activity and cost of those expedited activities.Activities are designated generically as A, B, and so on in order to avoid any copycat projects of this nature.
-Consider the project summarized in Table 11-8.Suppose in addition to the costs shown in the table, the mad scientist faces a $2,000 per week opportunity cost of not being in control of the world.Which of these activities should not be reduced in an effort to deliver a minimum cost (both project and opportunity cost) project?
A) F
B) H
C) G
D) E
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Once the crash cost per time period
Q2: Table 11-4<br>The following represents a project with
Q4: The value of work completed is computed
Q5: Budgets are computed using only ES times.
Q6: In PERT, the earliest start time for
Q7: For projects that have a daily fixed
Q8: Slack time in a network is the<br>A)amount
Q9: An IT project requires 6 activities.The table
Q10: CPM<br>A)assumes we do not know ahead of
Q11: In PERT, we assume that<br>A)the times to