    Given an Activity's Optimistic, Most Likely, and Pessimistic Time Estimates
Solved

Given an Activity's Optimistic, Most Likely, and Pessimistic Time Estimates

Question 54

Question 54

Multiple Choice

Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 5, and 14 days respectively, compute the PERT expected activity time for this activity.


A) 6
B) 7
C) 9
D) 5

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q49: The project described by: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="The

Q50: Table 11-8<br>A mad scientist has identified the

Q51: In PERT analysis, how is the pessimistic

Q52: Table 11-8<br>A mad scientist has identified the

Q53: PERT is a deterministic analysis tool allowing

Q55: Table 11-6<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Table 11-6

Q56: Before drawing a PERT or CPM network,

Q57: Which of the following is not a

Q58: Gantt charts and PERT diagrams provide the

Q59: Through the use of PERT/CPM, astute managers

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines