Multiple Choice
Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 5, and 14 days respectively, compute the PERT expected activity time for this activity.
A) 6
B) 7
C) 9
D) 5
Correct Answer:

Verified
Correct Answer:
Verified