Which of the following is not a concept associated with CPM?


A) normal time
B) probability
C) normal cost
D) crash cost

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q52: Table 11-8<br>A mad scientist has identified the

Q53: PERT is a deterministic analysis tool allowing

Q54: Given an activity's optimistic, most likely, and

Q55: Table 11-6<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Table 11-6

Q56: Before drawing a PERT or CPM network,

Q58: Gantt charts and PERT diagrams provide the

Q59: Through the use of PERT/CPM, astute managers

Q60: When crashing a project, all critical paths

Q61: Consider a project that has an expected

Q62: Given an activity's optimistic, most likely, and

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines