Multiple Choice
Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 14, and 18 days respectively, compute the PERT expected activity time for this activity.
A) 14
B) 12
C) 11
D) 13
Correct Answer:

Verified
Correct Answer:
Verified