    Given an Activity's Optimistic, Most Likely, and Pessimistic Time Estimates
Solved

Given an Activity's Optimistic, Most Likely, and Pessimistic Time Estimates

Question 98

Question 98

Multiple Choice

Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 14, and 18 days respectively, compute the PERT expected activity time for this activity.


A) 14
B) 12
C) 11
D) 13

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q93: Consider the following project schedule:<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg"

Q94: Table 11-3<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Table 11-3

Q95: The project described by: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="The

Q96: Table 11-4<br>The following represents a project with

Q97: Table 11-1<br>The following represents a project with

Q99: Given an activity's optimistic, most likely, and

Q100: The value of work completed for an

Q101: Draw the PERT network associated with the

Q102: Which of these statements is best?<br>A)PERT is

Q103: Table 11-6<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Table 11-6

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines