Multiple Choice
Table 11-6
-Which activities are part of Table 11-6's critical path?
A) A-B-E-G-H
B) A-C-E-G-H
C) A-D-G-H
D) B-F-H
Correct Answer:

Verified
Correct Answer:
Verified