Multiple Choice
Which of these statements is best?
A) PERT is a network technique similar to CPM, but PERT allows for project crashing, whereas CPM does not.
B) In PERT, the most likely completion time of an activity is used to represent that activity's time within a project.
C) The expected completion time and variance of an activity is approximated by the normal distribution in a PERT analysis.
D) PERT was developed for a project for which activity or task times were uncertain.
Correct Answer:

Verified
Correct Answer:
Verified
Q97: Table 11-1<br>The following represents a project with
Q98: Given an activity's optimistic, most likely, and
Q99: Given an activity's optimistic, most likely, and
Q100: The value of work completed for an
Q101: Draw the PERT network associated with the
Q103: Table 11-6<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Table 11-6
Q104: Figure 11-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Figure 11-1
Q105: PERT and CPM are quantitative analysis tools
Q106: Table 11-1<br>The following represents a project with
Q107: Table 11-7<br>A project manager calculated early and