    Consider a Project That Has an Expected Completion Time of 60
Solved

Consider a Project That Has an Expected Completion Time of 60

Question 29

Question 29

Multiple Choice

Consider a project that has an expected completion time of 60 weeks and a standard deviation of five weeks.What is the probability that the project is finished in 70 weeks or fewer? (Round to two decimals.)


A) 0.98
B) 0.48
C) 0.50
D) 0.02

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q24: PERT stands for<br>A)probabilistic evaluation and review technique.<br>B)program

Q25: Table 11-8<br>A mad scientist has identified the

Q26: The first step in planning and scheduling

Q27: In PERT/CPM, what is meant by the

Q28: Table 11-2<br>The following represents a project with

Q30: CPM stands for<br>A)critical path management.<br>B)critical project management.<br>C)critical

Q31: The process of smoothing out the utilization

Q32: Table 11-4<br>The following represents a project with

Q33: Table 11-5<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Table 11-5

Q34: The crash time of an activity represents<br>A)the

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines