Multiple Choice
PERT stands for
A) probabilistic evaluation and review technique.
B) program evaluation and review technique.
C) probability of expected run times.
D) program of expected run times.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q19: Table 11-4<br>The following represents a project with
Q20: An IT project requires 6 activities.The table
Q21: Which of the following statements about project
Q22: Consider the tasks, durations, and predecessor relationships
Q23: Given the following small project, the critical
Q25: Table 11-8<br>A mad scientist has identified the
Q26: The first step in planning and scheduling
Q27: In PERT/CPM, what is meant by the
Q28: Table 11-2<br>The following represents a project with
Q29: Consider a project that has an expected