Table 11-8
A mad scientist has identified the ten steps required to create a race of atomic supermen to complete his plans for world conquest.The estimated time in weeks and cost in US dollars appear in the table along with the shortest possible duration for each activity and cost of those expedited activities.Activities are designated generically as A, B, and so on in order to avoid any copycat projects of this nature.
-Consider the project summarized in Table 11-8.Suppose in addition to the costs shown in the table, the mad scientist faces a $2,000 per week opportunity cost of not being in control of the world.Which of these activities should be crashed in an effort to deliver a minimum cost (both project and opportunity cost) project?
A) F
B) H
C) D
D) C
Correct Answer:

Verified
Correct Answer:
Verified
Q20: An IT project requires 6 activities.The table
Q21: Which of the following statements about project
Q22: Consider the tasks, durations, and predecessor relationships
Q23: Given the following small project, the critical
Q24: PERT stands for<br>A)probabilistic evaluation and review technique.<br>B)program
Q26: The first step in planning and scheduling
Q27: In PERT/CPM, what is meant by the
Q28: Table 11-2<br>The following represents a project with
Q29: Consider a project that has an expected
Q30: CPM stands for<br>A)critical path management.<br>B)critical project management.<br>C)critical