Multiple Choice
Table 12-2
The following represents a project with four activities. All times are in weeks.
-According to the data in Table 12-2, what is the critical path?
A) A-B
B) A-C
C) B-D
D) A-B-C-D
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified