    In PERT Analysis,the Probability of the Optimistic Time Occurring Should
Solved

In PERT Analysis,the Probability of the Optimistic Time Occurring Should

Question 4

Question 4

Multiple Choice

In PERT analysis,the probability of the optimistic time occurring should be on the order of


A) 1/2.
B) 1/3.
C) 1/6.
D) 1/10.
E) 1/100.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q3: Activity B of a project has a

Q5: Given: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Given:

Q6: The project described by: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="The

Q7: Table 11-4<br>The following represents a project with

Q8: Figure 11-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Figure 11-1

Q10: PERT often assumes that time estimates follow

Q11: Table 11-4<br>The following represents a project with

Q44: The three time estimates employed in PERT

Q123: The optimistic time is the greatest amount

Q135: In CPM, crashing an activity that is

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines