menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Quantitative Analysis for Management Study Set 2
  4. Exam
    Exam 11: Project Management
  5. Question
    Activity B of a Project Has a Budgeted Cost of $50,000
Solved

Activity B of a Project Has a Budgeted Cost of $50,000

Question 3

Question 3

Multiple Choice

Activity B of a project has a budgeted cost of $50,000 and is 30% complete.The actual cost of the activity is $12,000.What is the activity difference?


A) -15,000
B) -3,000
C) 0
D) 3,000
E) 15,000

Correct Answer:

verifed

Verified

Related Questions

Q4: In PERT analysis,the probability of the optimistic

Q5: Given: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Given:

Q6: The project described by: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="The

Q7: Table 11-4<br>The following represents a project with

Q8: Figure 11-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Figure 11-1

Q10: PERT often assumes that time estimates follow

Q11: Table 11-4<br>The following represents a project with

Q44: The three time estimates employed in PERT

Q123: The optimistic time is the greatest amount

Q135: In CPM, crashing an activity that is

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines