Table 12-4 The Following Represents a Project with Known Activity Times. All

Question 47

Multiple Choice

Table 12-4
The following represents a project with known activity times. All times are in weeks. Table 12-4 The following represents a project with known activity times. All times are in weeks.   -Using the data in Table 12-4, what is the latest possible time that C may be started without delaying completion of the project? A)  0 B)  4 C)  8 D)  10 E)  None of the above
-Using the data in Table 12-4, what is the latest possible time that C may be started without delaying completion of the project?


A) 0
B) 4
C) 8
D) 10
E) None of the above