True/False
The variance of the project completion time is equal to the sum of the variances of all the activities.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q42: In a PERT analysis, how is the
Q94: In PERT,we assume that the project completion
Q95: The first step in planning and scheduling
Q96: Your company is considering submitting a bid
Q97: Table 11-4<br>The following represents a project with
Q98: Consider the tasks,durations,and predecessor relationships in the
Q100: CPM stands for Comprehensive Project Method.
Q101: Table 11-2<br>The following represents a project with
Q103: The expected time in PERT is<br>A)a weighted