Multiple Choice
Which of the following is not a decision variable when formulating the project crashing problem as a linear program?
A) the early finish times of critical activities
B) the early finish times of noncritical activities
C) the start time of the project
D) the finish time of the project
E) the early start times of all activities
Correct Answer:

Verified
Correct Answer:
Verified
Q59: An IT project requires 6 activities.The table
Q60: Given an activity's optimistic,most likely,and pessimistic time
Q61: Table 11-6 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Table 11-6
Q62: Slack time in a network is the<br>A)amount
Q63: Slack is the time an activity can
Q65: Table 11-5 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Table 11-5
Q67: Table 11-6 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Table 11-6
Q68: Given an activity's optimistic,most likely,and pessimistic time
Q105: PERT and CPM are quantitative analysis tools
Q114: One PERT/COST assumption is that money is