Solved

Figure 12-1 -Given the Network Shown in Figure 12-1, Assume That Completion

Question 73

Multiple Choice

Figure 12-1 Figure 12-1   -Given the network shown in Figure 12-1, assume that completion of B is delayed by two days. What happens to the project? A)  The critical path is extended by two days. B)  The start of activity F is delayed by two days. C)  The start of activity E is delayed by two days. D)  All of the above E)  None of the above
-Given the network shown in Figure 12-1, assume that completion of B is delayed by two days. What happens to the project?


A) The critical path is extended by two days.
B) The start of activity F is delayed by two days.
C) The start of activity E is delayed by two days.
D) All of the above
E) None of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions