The crash time of an activity represents


A) the normal time to complete an activity.
B) the most pessimistic time to complete an activity.
C) the incremental decrease in the time to complete an activity.
D) the shortened activity time.
E) None of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q43: Your company is considering submitting a bid

Q44: In PERT,we assume that<br>A)the times to complete

Q45: The expected completion time and variance of

Q46: Consider a project that has an expected

Q48: Table 11-2<br>The following represents a project with

Q49: Figure 11-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Figure 11-1

Q51: Table 11-1<br>The following represents a project with

Q52: Table 11-2<br>The following represents a project with

Q68: Gantt charts contain information about the time

Q131: Given the variability of the activity completion

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines