Multiple Choice
Given an activity's optimistic,most likely,and pessimistic time estimates of 2,10,and 20 days respectively,compute the PERT variance for this activity.
A) 3
B) 6
C) 9
D) 18
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified