Multiple Choice
Before a project team meeting, the ____ should determine whether a meeting is really necessary, the purpose of the meeting, and who needs to participate in the meeting.
A) the project team
B) the team member that identified a problem
C) the project manager
D) the customer
Correct Answer:

Verified
Correct Answer:
Verified