Multiple Choice
Contingency costs in the project costs estimate, also referred to as ____, are to cover unexpected situations that may come up during the project, such as items that may have been overlooked when the initial project scope was defined, activities that may have to be redone because they may not work the first time (redesigns) , or a high probability or high impact risk that may occur.
A) auxiliary funds
B) withholding
C) reserves
D) capital funds
Correct Answer:

Verified
Correct Answer:
Verified
Q93: In many cases, there will be a
Q94: The first method for determining _ assumes
Q95: Cumulative actual cost (CAC)should be calculated to
Q96: Calculate the forecasted cost at completion if
Q97: It is important to use the _
Q98: Consider a project that involves painting five
Q99: The cumulative actual costs of a project
Q100: Equipment costs in the project costs estimate
Q101: Allocating total project costs for the various
Q103: Managing cash flow involves making sure that