Multiple Choice
Allocating total project costs for the various elements to the appropriate work packages in the work breakdown structure will establish a ____ for each work package.
A) total allocated cost
B) total control cost
C) total quality cost
D) total budgeted cost
Correct Answer:

Verified
Correct Answer:
Verified