Multiple Choice
The first method for determining ____ assumes that the work to be performed on the remaining portion of the project or work package will be done at the same rate of efficiency as the work performed so far.
A) forecasted cost at completion
B) cumulative actual cost
C) cumulative earned value
D) cost performance index
Correct Answer:

Verified
Correct Answer:
Verified
Q89: Committed costs need to be treated in
Q90: Determining the earned value involves collecting data
Q91: As data are collected on _, including
Q92: The cost performance index (CPI)is a measure
Q93: In many cases, there will be a
Q95: Cumulative actual cost (CAC)should be calculated to
Q96: Calculate the forecasted cost at completion if
Q97: It is important to use the _
Q98: Consider a project that involves painting five
Q99: The cumulative actual costs of a project