Multiple Choice
The ____ is the amount that was actually spent to accomplish the work that was scheduled to be performed up to that point in time.
A) total budgeted cost (TBC)
B) cumulative budgeted cost (CBC)
C) cumulative actual cost (CAC)
D) cumulative earned value (CEV)